Project Schedule

November 2023

Minor construction begins

Winter 2023

Drainage, earthwork and temporary striping

Spring 2024

Major construction scheduled to take place through the end of 2025. Traffic control will be communicated in advance.

*Construction schedule is weather permitting and subject to change.
In future years, NDOT plans an additional phase of improvements which will widen, repave, and improve neighboring sections of U.S. 395 between Golden Valley Road and Stead Boulevard. Information on available phases is available at dot.nv.gov/northvalleys.