Traffic Control Week of December 1, 2023

North Valleys Project Traffic Control Update

Dear Stakeholder,

Construction will begin on Sunday, December 3, 2023 at 8 p.m. on southbound U.S. 395 between North McCarran Boulevard and Golden Valley Road. Construction on northbound U.S. 395 began in November. Drivers will see lane shifts and lane width reductions on both directions of highway 24/7.
The majority of construction operations can be expected Sunday nights through Saturdays.   

Ongoing

Speeds will be reduced to 55mph 24/7 through the work zone, with lanes slightly shifted.

Through winter, all lanes are anticipated to remain open for travel during daytime commute hours.

  • Lanes will be reduced to a minimum of one lane in each direction:
    • Northbound U.S. 395: between 8 p.m. and 11 a.m.
    • Southbound U.S. 395: between 7 p.m. and 5 a.m.
  • Intermittent ramp closures will take place between 9 p.m. and 5 a.m.
  • No two consecutive ramps will be closed in the same direction, and detour routes will be marked.

This is a multi-year project with anticipated completion in 2025. Beginning in early 2024, NDOT advises drivers to anticipate additional major construction impacts, including northbound U.S. 395 being reduced to two lanes and extended closure of North Virginia Street access to northbound U.S. 395 for bridge construction.

Please Note:

  1. Message signs will be in place notifying motorists of the work activities.
  2. Expect delays and use alternate routes when possible.

Sign-up to receive text alerts at https://slkt.io/YSd4, or text “NorthValleys” to 866-540-8466.